OpenSep 9, 2024
Electrical
Installed 4 kilns at ground floor without a building permit and the required approvals. The kilns are electrically powered. Code/Section: SFBC 103.A Monthly monitoring fee applies. Code/Section: SFBC 110A Table 1A-K
OpenMar 7, 2024
Electrical
Electrical work performed without benefit of electrical permit. A monthly monitoring fee will be assessed. Sec 110A, Table1A-K Code/Section: 89.120
OpenJul 18, 2022
Plumbing
A complaint investigation revealed work has commenced under a suspended permit. PA202208090143 was suspended on August 30, 2022 per request by SF department of City Planning. On August 12, 2022, the subject permit was issued by DBI authorizing the following: ¿ADD A NEW SHOWER & TOILIET IN (E) UPPER FLOOR GUEST ROOMS 4 & 8. RELOCATE SINKS AND CLOSETS AS SHOWN PER PLANS. WORK IS CONTINUATION OF WORK STARTED UNDER PA202010217081. NO CHANGE TO UNIT SIZE in SRO.¿ On August 4th 2022 the project representative was contacted due to concerns from complainant regarding preparing work in unit #8. On August 8th 2022 The property was inspected based on multiple concerns of ongoing work in unit 8 and 14. Plans were reviewed and they verify that work in unit 14 is within the scope of the approved and issued building permit. Access provided to unit # 8. No major construction or demolition of walls were observed. Contractor was advised not to do any work in unit #8 and that a building permit is required for any remodel work in unit # 8 On August 30th 2022 DBI scheduled an inspection for PA202010217081 at 9 a.m. to review all complaints. The inspector arrived at 9:15 a.m.and found no one on site,.The inspector called the contractor and the contractor said that he was still in route to the inspection location. The inspector informed the contractor that he would need to reschedule the inspection due to the inspector¿s limited time schedule. The contractor agreed. On September 12th 2022, a site visit with, Henry Karnilowicz and contractor occurred. New work observed in unit # 8 (Removal of plaster in some of the walls, framing of partition for shower enclosure, adding framing material to door opening to enclose it and rough plumbing work) despite permit being suspended. Specified to both Mr. Karnilowicz and contractor that work should NOT continue in units 4 or 8 until work for the façade under PA202010217081 has been completed and planning gives approval for reinstating PA202208090143 Code/Section: SFBC106A.4.5, 102A Monthly monitoring fee applies. Code/Section: SFBC 110A, Table 1A-K
OpenFeb 12, 2021
Heating equipment
New bathrooms being constructed on 2nd floor in guest rooms 5 and 9, and in boiler/storage room area. Kitchen added in guest room #5. PA 202010076054 and 202010146425 issued for bathroom remodels have been revoked. Code/section SFBC 103A Monthly monitoring fee applies. Code/Section: SFBC 110A, Table 1A-K
OpenFeb 12, 2021
Permits & unpermitted work
COMMERCIAL - GAS, DWV, H20 PIPING AND FIXTURES INSTALLED WITHOUT A PERMIT IN GROUND LEVEL COMMERCIAL SPACE. WATER HEATER INSTALLED WITHOUT PERMIT. MECHANICAL - FURNACES INSTALLED WITHOUT A PERMIT. PENALTY 9X $302.25 Code/Section: CPC Chapters 1, 3, 4, 5, 6, 7, 12. CMC Chapters 1, 3, 8, 9 Monthly monitoring fee applies. Code/Section: SFBC 110A, Table 1A-K
OpenFeb 8, 2021
Electrical
Electrical equipment, wiring and systems deemed to be hazardous to human life or structure safety. Electrical work performed without an electrical permit: installation of new electrical service. Code/Section SFEC 89.126 (A), 89.123 (C) Monthly monitoring fee applies. Code/Section: SFBC 110A, Table 1A-K
OpenJan 28, 2021
Plumbing
RESIDENTIAL - UNITS # 5, 9, AND UTILITY ROOM PLUMBING INSTALLED WITHOUT A PERMIT. GAS DWV, H2O PIPING AND FIXTURES INSTALLED. - WATER HEATER ALSO INSTALLED. PENALTY 9X $534.75 Monthly monitoring fee applies. Code/Section: SFBC 110A, Table 1A-K
OpenMay 18, 2020
DBI code violation
A complaint has been filed with this department regarding unpermitted construction at above location. New framing partitions installed in commercial space. Building permit application # 201906264417 has been filed for tenant improvement but not yet issued. Code/Section: FBC 103A, 102A Monthly monitoring fee applies. Code/Section: SFBC 110A, Table 1A-K